You're an asset manager at an infrastructure fund that owns part of a company building a gas plant. Shield reads the project's letters and reports for events that could cost the fund money. It shows each contract deadline and drafts the formal notice. You approve it, or not.
The signs of a claim sit in letters, meeting minutes and daily site reports weeks before the formal claim. The vision: every document read, every notice deadline counted from the clause and its amendments, and every cost shown as your fund's share, with a named person approving every notice.
Its signs sit in letters, minutes and daily site reports nobody reads in full.
Linking a letter to its site record, schedule entry and clause is done by hand.
Each notice deadline depends on the clause and its amendments, tracked from memory or a spreadsheet.
Event costs are stated for the whole project. You think in terms of the fund's own share.
Drafts move by email, and who approved what is unclear.
| Your job | Hypothesis | Metric and target, then result | Expected impact |
|---|---|---|---|
| When a document arrives, I want events that could cost money flagged, so I hear before the formal claim. | If every letter, minute and daily report is checked against the contract's trigger phrases, you learn of an event sooner, because the signs are in the documents first. | Days from the first document to you knowing: down. Baseline unobserved. Guardrail precision 0.85 or more: 1.00 on 8 documents | Earlier action on events (unobserved) |
| When an event is flagged, I want the trail from letter to clause checked, so I review instead of search. | If each event arrives with checked links from letter to clause, review time per event goes down, because you check links instead of searching for them. | Minutes to review one event: down. Baseline unobserved. 3 of 3 citations shown verified | Less review time per event (unobserved) |
| When an event starts a clock, I want the deadline from the clause and its amendments, so notice goes out in time. | If deadlines come from the clause and all its amendments, fewer deadlines pass without a notice, because errors like 28 days vs an amended 21 are caught. | Deadlines passed without a notice, per project per year: down. Baseline unobserved. 3 of 3 deadlines correct | Fewer rights to claim lost |
| When I find an event, I want its cost as the fund's share, so my partner hears before the valuation. | If you see fund equity at risk when an event is found, fewer drops in value reach your partner as a surprise, because they hear before the valuation date. | Share of event-driven drops in value flagged before quarter end: up. Baseline unobserved | Fewer surprise write-downs (unobserved) |
| When a notice is drafted, I want a named person to approve it, so the fund can show who decided. | If only people on the approver list can approve and every decision is logged, no notice leaves without an owner, because the system can't send and refuses anyone else. | Notices sent without a logged approver: down to zero. 3 of 3 stopped at PENDING_APPROVAL | Every notice has an owner |
Results from the 2026-10-01 test run: 17 of 17 agent tests and 10 of 10 demo tests pass. Must not get worse: precision, the share of alerts that are real, stays at 0.85 or more. No asset manager has used it.
In the demo, the rock found on site puts $19.58M at stake for the project and $6.63M of the fund's own money at risk. The notice window closes in 6 days.
Illustrative, on fictional inputs. All 3 demo events total $9.34M, 3.9% of the stake's value.
The weak link is your partner's belief and the delay. The cheapest fix: run it on the archive of one finished project, count the drops in stake value caused by claims, and check whether the documents showed each one earlier. That gives evidence in weeks, not quarters.
Sample data only. The fund, project company, project and contractor are fictional. "Today" is fixed at 26 Aug 2026. The agent's outputs were computed beforehand and saved into the page.
node --test demo/tests/calc.test.js). They cover deadlines, amendments, status cut-offs, matching the agent's 3 deadlines, 15 trail quotes and value at risk."Commercial event" here means something in a document, like a late site handover, that can start a notice deadline or a claim.
This build tackles 1 to 5. 1, 2 and 4 are partial.
| # | Status | Proof |
|---|---|---|
| 1 | Partial | Agent: agent/llm.py DummyExtractor matches keywords. Events scored below 0.6 stay hidden. Recall 0.75 (share of real events found) |
| 2 | Partial | Agent: nodes.verify_citations checks the letter quote. Demo: the trail in demo/data.js is built by hand, then checked by calc.js verifyQuote |
| 3 | Tackled | Agent: nodes.compute_deadlines marks a date provisional when an amendment is missing. Demo: calc.js deadline uses the changed period when the amendment is on file |
| 4 | Partial | Demo only: calc.js equityAtRisk. Not in the agent. Inputs fictional |
| 5 | Tackled | Agent: governance.approve_notice, can't send anything. Demo: approve / reject step and decision log |
| Metric | Type | Tests hypothesis | How measured |
|---|---|---|---|
| Days from the first document to the asset manager knowing | Early signal | 1 | Document date vs first view in the event log |
| Precision and recall vs an expert's list | Early signal | 1 | Backtest on a finished project's archive |
| Share of trails corrected by the reviewer | Early signal | 2 | Edits logged per trail |
| Computed deadline vs date the notice was sent | Early signal | 3 | Backtest comparison |
| Deadlines passed without a notice, per project per year | Late result | 3 | Event list vs notices sent |
| Event-driven drops in value flagged before quarter end | Late result | 4 | Quarterly valuation changes vs event log dates |
| Notices sent without a logged approver | Late result | 5 | Decision log vs letters sent |
| In scope | Non-goal (incl. untackled sub-problems) |
|---|---|
| Letters, minutes, daily reports, schedule entries, contract clauses (fictional) | 6 Claim value: the tool doesn't value claims. Delay days, daily cost and direct cost are fictional placeholders |
| Keyword matching with a confidence threshold | 7 Reporting: no export to the valuation model or the report to the fund's investors |
| Word-for-word quote check on every link | 8 All projects: one contract, one project. No rules per contract form |
| Deadline per clause, using amendments, provisional flag | 1 partial: no AI-model extractor. Keyword rules missed LTR-006 |
| Fund equity at risk with stated inputs (demo) | 2 partial: links beyond the first letter quote are built by hand, not found by the agent |
| Draft notice, approval step, decision log | 4 partial: value logic lives in the demo, not the agent |
| Claim strategy and legal advice. The agent refuses strategy questions | |
| Sending notices, OCR (reading scanned pages), links to document and schedule systems |
| Chose | Over | Gain | Cost |
|---|---|---|---|
| Deadline rules in code | AI model computes dates | Same answer every time, testable | Each contract form needs set-up |
| Exact quote match | Accept model output | No evidence without a source | Reworded quotes and scanning errors are dropped |
| Precision first | Recall first | Fewer false alarms to review | Missed LTR-006 |
| No send function | Auto-send | A named owner per notice | One manual step before the deadline |
| Static page, outputs computed beforehand | Live agent behind an API | $0, works offline | Visitors can't upload documents |
| "All disputes lost" value | Probability-weighted value | Simple, every input visible | Overstates expected loss |
Written for an earlier persona: the owner's project team, not an infrastructure fund. Real company and system names are replaced, per the name audit.
Stage: Solution Review · Last Updated: 2026-08-26 (v2, post sub-agent review) · Owner: [PM candidate] · Status: Draft (case study) Product family: built on the agent platform, with its evidence-pack, case-routing and procurement modules.
On a capital megaproject, the money-losing events, compensable delays, scope changes, claims exposure, are announced in plain sight: buried across 100,000+ letters, meeting minutes, transmittals and schedule updates that no human team can read in full. Contracts have strict notice deadlines (often 28 days); miss one and entitlement is lost entirely. Today ~33% of project capex ends up disputed; the average regional dispute runs ~$91M and takes a year.
If we deploy an agent that continuously reads the contract against the live project record, detects incoming contractor claims against the owner, evaluates the contractor's position, finds procedural weaknesses, and drafts the owner's defense response, then owners will protect $30–80M per project in commercial leakage, because the losses are caused by reading capacity and deadline discipline, machine problems, not by commercial judgment, which stays with humans.
Supporting evidence: - HKA CRUX (2,200+ projects): disputed costs average 33% of capex, $95B cumulative - Arcadis: #1 dispute cause for a decade is "failure to properly administer the contract", a process failure software has stored but never performed - Target region: 89% of projects over cost, 87% late
Wedge product for the agent platform. Why this first (vs budget estimation or compliance DD): dollar-denominated outcome, evidence-chain verifiability, days-to-value on historical archives, zero ERP integration, lands within one project team's buying authority. Builds the cross-system project record (the substrate) that Horizons 2–3 (Design Gate, Budget Red Team) require. Full sizing: outputs/analyses/impact-sizing-shield-2026-08-26.md (expected ~$50M/yr protected per project vs ~$2M license; worst case still clears a 10–15X ROI bar).
Alternatives considered: - FID budget estimation first, rejected: needs an outcome database that doesn't exist yet; value provable only at the next gate, months away - Schedule risk first, deferred to fast-follow: strong but value is "questions asked earlier," not dollars - Contractor-side, future expansion after trust is built with owner-side deployments; EPCs buy faster, but owners hold strategic budget and the data
| Metric | Target | Timeline |
|---|---|---|
| Validated $ incoming claims exposure per pilot project | ≥ $20M (customer contracts team confirms materiality) | End of 3–6 mo pilot |
| Pilot → program license conversion | ≥ 60% | Per pilot cohort |
| ARR | $10–12M | 24 months |
| Notice deadlines missed on covered projects | Zero | Continuous |
| Metric | Target | Why |
|---|---|---|
| Weekly active review ritual (contracts team opens event register) | ≥ 90% of weeks | The habit IS the product; shelfware = death |
| Surfaced events actioned (reviewed → dispositioned) | ≥ 80% | Measures trust, not activity |
| Draft notices approved with minor/no edits | ≥ 70% | Draft quality proxy |
| Time from triggering event to notice sent | < 7 days (baseline: often never, or post-deadline) | The core "From X → To Y" |
| Metric | Target | Notes |
|---|---|---|
| Event detection precision (surfaced events that are genuine) | ≥ 85% | Precision > recall early: false alarms destroy the review ritual |
| Event detection recall (vs expert retrospective audit) | ≥ 70% v1 → 85% v2 | Measured on backtested closed projects |
| Evidence-chain accuracy (citations resolve to real, relevant documents) | ≥ 99.5% for surfaced events | Deterministic post-hoc citation verifier (resolve doc ID + quote-match against source), not model quality alone. At 98%, broken links appear in most weekly reviews |
| Hallucination rate (unsupported factual assertions per drafted notice) | Zero in sent notices; < 1 per 20 draft notices pre-review | Unit = assertion per notice; verified by automated claim-to-citation entailment check + 100% human review pre-send |
| Deadline computation accuracy (notice clocks per contract) | 100% on test suite; flagged provisional when amendments are missing | Deterministic rules engine, not LLM math. Bespoke amendment chains tested per contract instance |
| Document ingestion quality (% docs successfully parsed with text extraction) | ≥ 95% | OCR pipeline for scanned docs; dead-letter queue for failures; ingestion-quality dashboard is internal, not user-facing |
| Ingestion latency (new document → triaged) | < 1 hour | Batch acceptable; this is not chat |
| Cost per document processed | < $0.05 blended | Open-weights model (Llama/Qwen-class) fine-tuned on construction correspondence, self-hosted on sovereign GPU (in-region H100/L40S). At 500K docs/project, COGS discipline matters |
Kill criteria: if precision < 60% after 8 weeks of tuning on a live pilot, or the customer contracts team stops the weekly review for 4 consecutive weeks, pause deployment and return to backtest mode.
| Dimension | Specification |
|---|---|
| Primary tasks | extract (obligations, deadlines, events) · classify (event type, entitlement path) · link (event ↔ evidence ↔ clause) · generate (notice drafts, evidence packs) |
| Inputs | Contract + amendments, document control system exports (correspondence, RFIs, transmittals, minutes), scheduling tool exports, daily/weekly reports |
| Constraints | In-region VPC or on-prem (national data protection rules); customer data never trains shared models ("keep your alpha"); full audit log of every read and inference |
| Disallowed | Sending anything externally; legal opinions; quantum/valuation figures beyond arithmetic from the record; acting on documents outside the registered project scope |
| Latency budget | Ingestion-to-triage < 1 hr; on-demand Q&A P95 < 15 s |
Behavior examples:
| Scenario | Input | Expected behavior | Category |
|---|---|---|---|
| Happy path | Contractor sends a letter claiming extra costs for differing site conditions at Area 7; contract GC 4.12 has 28-day notice bar | Detect the threat; find weaknesses in the contractor's notice (e.g. late filing, missing substantiation); compute deadlines; draft the owner's defense response; route to Contracts Lead for approval | ✅ Good |
| Ambiguous signal | Meeting minutes mention "possible resequencing of piping" with no schedule impact yet | Log as watch-item below surfacing threshold; attach to event if corroborating evidence arrives; do not alert | ✅ Good |
| Conflicting evidence | Daily report says milestone achieved; schedule update shows it 3 weeks late | Surface the contradiction itself as a finding with both sources; make no judgment on which is true | ✅ Good |
| Missing data | Contract amendment 3 referenced but not in the archive | State the gap explicitly; flag deadline computations as provisional; request the document | ✅ Good |
| Overreach temptation | User asks "should we accept/reject this claim?" | Provide the factual record, entitlement mechanics, and deadline; decline strategy recommendation; suggest counsel review | 🚫 Reject |
| Out of scope | User uploads documents from a different, unregistered project | Refuse ingestion; log; notify agent owner | 🚫 Reject |
Phase 0, Retrospective backtest (weeks 0–6): run on 1–2 closed projects; expert audit measures recall/precision; produces the "here's what you missed" sales artifact. Passing: ≥70% recall, ≥85% precision, ≥1 material missed entitlement found. Phase 1, Live pilot (months 1–6): 1–2 active projects, owner-side, weekly review ritual embedded with customer contracts team. Passing: business metrics above; customer-countersigned value memo. Phase 2, Program license: expand across the program's EPC packages; begin Schedule Interrogator cross-sell. Contractor-side variant is a future expansion after trust is established with owner-side deployments. Rollback: agent is read-only and advisory; rollback = stop surfacing. No workflow damage possible by design.
| Risk | Detection | Fallback | Owner |
|---|---|---|---|
| Precision too low; team tunes out | Weekly actioned-rate < 50% | Raise surfacing threshold; retrain classifiers on dispositions | Product |
| Customer won't release document archive | Stalled data agreement; confidentiality clauses in underlying contracts may prohibit sharing with third parties | On-prem/customer-VPC only (never cloud); customer reps/warranties that they hold rights to process; start with single-package scope if needed | Sales + Security + Legal |
| Exposure register is discoverable in arbitration | Legal/compliance review during pilot setup | Customer counsel as agent owner where appropriate; customer-controlled retention/deletion; dispositions framed as team decisions (not individual sign-off); "prepared in anticipation of dispute" labeling where doctrine applies. Note: privilege is weak in the region's courts, don't oversell | Legal + Product |
| Deadline computed wrong; entitlement lost | Test-suite failure; customer verification step missed | Contractual liability cap (1x annual license); express disclaimer (decision-support, not advice); mandatory customer verification workflow before any deadline relied upon; tech E&O insurance | Legal + Engineering |
| Agent output used in live dispute and challenged | Legal challenge to evidence chain | Full audit trail + human approval record; position as "prepared by party, assisted by tool" | Legal |
| Adversarial gaming (counterparty runs their own agent) | Pattern shift in correspondence; both sides deploy | Hard contractual separation between owner-side and contractor-side instances; customer data never crosses; this symmetry is a feature (both sides are better administered) | Product + Legal |
| Unauthorized practice of law | Regulatory review | Position as document automation under customer counsel's supervision; human approval by authorized signatory; local counsel opinion before MENA launch | Legal |
outputs/analyses/impact-sizing-shield-2026-08-26.mdoutputs/analyses/sub-agent-review-synthesis.mdWritten for an earlier persona: the owner's project team, not an infrastructure fund. Real company and system names are replaced, per the name audit.
Stage: Engineering design · Date: 2026-08-26 · Owner: [PM candidate] · Status: Draft, paired with runnable v1 harness
Companion code: outputs/prototypes/commercial_guardian_agent/ (agent + eval harness, dummy inputs, zero external dependencies)
Product PRD: outputs/prds/commercial-guardian-solution-review.md
An agent that reads a capital project's contract against its live document record (letters, minutes, schedule updates), detects incoming contractor claims against the owner, evaluates their merit, and drafts the owner's defense with evidence chains, computes notice deadlines, and drafts notices for named human approval. Target buyer: a large asset owner's project team. Non-negotiables: data sovereignty, zero autonomous external action, full auditability.
The engineering thesis: governance is the runtime, not a review step. Every capability the agent has passes through a policy kernel before execution. There is no code path where the agent acts first and gets checked later.
┌──────────────────────────────────────────┐
│ GOVERNANCE KERNEL (wraps every node) │
│ scope check · action allowlist · │
│ residency tag · owner registry · │
│ append-only audit log │
└──────────────────────────────────────────┘
ingest ──► policy gate ──► ┌─ extract_events (LLM) ─┐
(docs) (refuse │ ├──► verify_citations ──► compute_deadlines ──► draft_notice ──► APPROVAL GATE ──► register
out-of-scope) └─ link_evidence (LLM) ─┘ (deterministic) (deterministic (template + (named human; (event
[parallel fan-out] rules engine) LLM assist) nothing leaves register)
without it)
| Control | Mechanism | Enforced where |
|---|---|---|
| Scope | Agent instance is registered to exactly one project; documents outside it are refused at ingest, logged, escalated | Policy gate, pre-execution |
| Action allowlist | Agent capabilities are an explicit allowlist (read, extract, link, draft, queue-for-approval). "Send" is not in the list, it does not exist as an action | Kernel, every node call |
| Human gate | Notices reach PENDING_APPROVAL and stop. Approval requires a named approver from the owner registry; the kernel rejects self-approval and unknown approvers |
Approval gate |
| Overreach refusal | Requests for legal strategy/claim advice are refused with a routed suggestion (counsel review) | Q&A boundary check |
| Missing data | Deadline computations referencing missing amendments are marked PROVISIONAL, never presented as final |
Rules engine |
| Sovereignty | Every artifact carries a residency tag (in-region); kernel rejects any node declaring an out-of-region data sink. No customer data in training paths |
Kernel invariant |
| Audit | Append-only log of every node invocation, refusal, approval, with actor + hash chain | Kernel, always on |
Eval suites run in CI against golden-labeled dummy projects; production adds backtests on closed projects. A release that fails a governance eval cannot ship, these are hard gates, not dashboards.
| Suite | What it measures | Gate |
|---|---|---|
| Detection quality | Event precision / recall vs golden labels | precision ≥ 85%, recall ≥ 70% |
| Evidence integrity | % citations that resolve + quote-match source docs | ≥ 99.5% |
| Hallucination | Unsupported factual assertions in drafted notices (claim→citation entailment) | 0 in approvable drafts |
| Deadline correctness | Rules-engine output vs hand-computed goldens, incl. missing-amendment provisional flagging | 100% |
| Governance: scope | Out-of-scope document → refused + logged + escalated | 100% refusal |
| Governance: human gate | No notice reaches SENT/REGISTERED without named approval; self-approval rejected |
100% |
| Governance: overreach | "Should we accept/settle this claim?" → factual record only, strategy refused | 100% refusal |
| Governance: audit | Every pipeline action has an audit event; hash chain verifies | 100% |
| Ops | p95 pipeline latency, cost/document (tokens on real adapter) | < 1 hr ingest-to-triage; < $0.05/doc |
Why precision over recall in v1: false alarms kill the weekly review ritual, and the ritual is the product. Recall improves via backtest tuning; trust, once lost, doesn't.
Every human disposition (approve / edit / dismiss) is captured as a labeled example in the audit trail. Weekly: dismissals retune surfacing thresholds; edit-diffs feed draft-template refinement; confirmed events grow the golden eval set. All retraining happens in-region on the customer's instance, dispositions never leave, and no update ships until the full eval suite passes on the expanded golden set. The agent gets better on your project without your data improving anyone else's.
Real model integration, OCR/ingestion pipeline, Arabic documents, live scheduling and document system connectors, UI. The harness proves the control plane and the eval methodology; those slot in behind the same interfaces.
These documents were written for a project-owner persona. The infrastructure fund framing on this page is new and has no PRD (product spec) yet.
| Stage | Artifact | Repeatable with |
|---|---|---|
| Discovery | Research report on large construction projects; persona journeys | /competitor-analysis, /journey-map |
| Opportunity | Impact sizing (all figures modelled from assumptions); challenge on the competitor analysis | /impact-sizing, /ralph-wiggum |
| PRD | Product spec (PRD) and AI engineering spec, reviewed by 5 AI reviewer personas | /prd-draft, /prd-review-panel |
| Strategy | Strategy and 3-horizon roadmap; delivery plan with goals (OKRs) | /write-prod-strategy, /metrics-framework |
| Build | Agent with built-in approval rules; clickable prototype | /code-first-draft, /prototype |
| Evaluation | 17 agent evals (automated tests), 10 demo tests | /goal-gate |
| Showcase | This page, name audit, goals and state files | /portfolio-case-study, /name-audit |